  • Week - 01 introduction and brain storming
  • Week - 02 brain storming continues, proposal set, research into visual cues
  • Week - 03 visual cues continues, planning of shot and test concepts continues
  • Week - 04 planning continues then at the later part, 1st shooting of 3 secs at shop(might have more then 1 view). Then 3 sec of an action in same area(eg. someone walking by(most likely shop owner).
  • Week - 05 filming continues if not done, reference photos taken in case modelling is needed
  • Week - 06 modeling continues, editing via matte painting starts
  • Week - 07 blocked for matte painting and editing
  • Week - 08 blocked for matte painting and editing
  • Week - 09 blocked for matte painting and editing
  • Week - 10 blocked for matte painting and editing
  • Week - 11 putting it together and rendering
  • Week - 12 just in case some more time is needed for any of the previous items.